2020-09-13 Sunday
Start of the day pictures...
Morning timelapse #1 - 43s (22m real time)
P, A and H work on the subfascia on the back (West) of the shed
Morning timelapse #2 - 2m 48s (1h 24m real time)
D and P set up to start work on the subfascia on the front
D works on extending the studs up through the "triangle" south wall
P waters
D and P work on subfascia installation while D continues to add studs in the triangle
Afternoon timelapse #1 - 1m 51s ( 55m real time)
D works on the triangle while P works on the East subfascia
Dry-fitting the remaining subfascia piece convinces us that we may need to trim some of the remaining rafters
Afternoon timelapse #2 - 8m 30s ( 4h 15m real time)
D and P work on trimming some of the remaining rafters
D gets P started on cutting the fascia for the N and S walls (which P works on off-camera)
D trims rafters
D continues work on the triangle supports for the N wall
P installs the remaining subfascia on the E (front)
H helps P install fascia on N side
D works on N wall triangle parts
H helps a bit with S fascia
P takes over and installs S fascia
D works on trimming the remaining rafter blocking that are too tall
P fixes a bad nail in the N fascia
P puts up the first piece of the E fascia (a narrow piece that will get an extension added later)
End of the day photos...