2020-09-13 Sunday

Start of the day pictures...

Morning timelapse #1 - 43s (22m real time)

  • P, A and H work on the subfascia on the back (West) of the shed

Morning timelapse #2 - 2m 48s (1h 24m real time)

  • D and P set up to start work on the subfascia on the front

  • D works on extending the studs up through the "triangle" south wall

  • P waters

  • D and P work on subfascia installation while D continues to add studs in the triangle

Afternoon timelapse #1 - 1m 51s ( 55m real time)

  • D works on the triangle while P works on the East subfascia

  • Dry-fitting the remaining subfascia piece convinces us that we may need to trim some of the remaining rafters

Afternoon timelapse #2 - 8m 30s ( 4h 15m real time)

  • D and P work on trimming some of the remaining rafters

  • D gets P started on cutting the fascia for the N and S walls (which P works on off-camera)

  • D trims rafters

  • D continues work on the triangle supports for the N wall

  • P installs the remaining subfascia on the E (front)

  • H helps P install fascia on N side

  • D works on N wall triangle parts

  • H helps a bit with S fascia

  • P takes over and installs S fascia

  • D works on trimming the remaining rafter blocking that are too tall

  • P fixes a bad nail in the N fascia

  • P puts up the first piece of the E fascia (a narrow piece that will get an extension added later)

End of the day photos...